Canadian Malartic
Mining sector
Scheduled maintenance
Unplanned shutdown
Year: 2016 (in progress) to 2017
Location: Canadian Malartic
Value of work: $4 million / $1.5 million annual contract in planned shutdown
Challenges met
Complete the work within the agreed upon schedule and quickly react to the additional work that required the dispatch of 40 additional men. In order to prevent work-related accidents, our CNESST manager WSIB ensured that two safety meetings were held daily throughout the shutdown.